September 2024

Intro Background Image

Earthworks of the 2nd p.k. – 60% (work on Section 3 has been completed);
Horizontal waterproofing of the 2nd floor –10% (works under Section 3 are in progress);
Foundation slabs of the 1st p.k. – completed;
Foundation slabs of the 2nd p.k. – 10% (works under Section 3 are in progress);
Vertical waterproofing of the 1st p.c. – 60% (waterproofing of the trade section and section 4 is being carried out);
Backfilling of the 1st p.c. – 50% (filling of Sections 5 and 6 is completed);
Monolithic frame to department (0.000) of the 1st p.c. – 90% (work is being carried out on the trade section); Masonry of walls and partitions of the 1st p.c. – 5% (works will be carried out on the 2nd and 3rd floors of Section 6, masonry of parapets on Section 5 has begun);
Arrangement of ventilation ducts and chimneys of the 1st p.c. – 5% (work has begun on the masonry of the ventilation ducts of Sections 5 and 6).

Sales department

Lviv, square Old Market, 8

Facebook Icon Instagram Icon