Section 1
- Completion of foundation slab concreting
- Concreting of parking walls
Section 2
- Installation of the monolithic frame
- Waterproofing of the parking area
Section 3
- Masonry of walls and partitions
- Waterproofing works
Section 4
- Installation of internal engineering networks
- Roofing works
- Installation of windows
Section 5
- Plastering works in progress
- Installation of internal engineering networks
- Facade works in progress
Section 6
- Plastering works in progress
- Installation of internal engineering networks
- Facade works in progress
- Elevator installation in progress