May 2024

Intro Background Image

Works performed as of the beginning of May:

Dismantling works – completed;

Work on the pit of Section 4 has been completed, work on the commercial building has begun;

Started work on Section 1 – 5%;

Horizontal waterproofing of the 1st p.c. – 60% (completed works on section waterproofing);

Vertical waterproofing of the 1st p.c. – 40% (waterproofing of sections 6 and 5 is being carried out);

Foundation slabs of the 1st p.k. – 60% (completed works on the foundation slab of section 4);

Monolithic frame to department 0.000 of the 1st p.c. – 50% (completed work on section 5, ongoing work on section 4);

The monolithic frame is higher than 0.000 of the 1st p.c. – 8% (concreting work on the 2nd floor of section 6 is underway, work on section 5 has begun).