Section 1 – Pile installation completed, foundation slab installation started.
Section 2 – Monolithic works on the underground part are in progress, waterproofing works continue.
Section 3 – Monolithic works on the 7th floor are ongoing, masonry of ventilation ducts is being carried out, and waterproofing works are in progress.
Section 4 – Masonry work is in progress.
Section 5 – Wall plastering has begun, windows are being installed, electrical and plumbing works continue, and roofing installation is underway.
Section 6 – Masonry work continues, roofing installation is in progress, and window structures are being installed.