Works being carried out as of the beginning of March in the City House residential complex:
Dismantling works – completed;
Earthworks – excavation works for section 5 have been completed and soil development has begun in the area of section 4;
Horizontal waterproofing of the 1st floor – waterproofing of the residential part of section 5 is starting;
Foundation slabs of the 1st p.k. – arrangement of crushed stone and concrete preparation of section 5 is completed;
Monolithic frame to department 0.000 of the 1st p.c. – work on vertical structures on the -1st level of the parking lot of section 6 is being carried out, and work on the floor slab on the dept. floor – 1st level of the parking lot of the stylobate part of section 5