June 2025

Hexahedrons icon
ЖК City House у Львові

Section 1
The concreting of the foundation plate is completed
Concretion of parking walls
Section 2
Arrangement of monolithic frame 2 floors
Parking waterproofing

Section 3
Masonry of walls and partitions is completed
Arrangement of waterproofing

Section 4
Installation of internal engineering networks
The roof arrangement is completed
Windows are installed
Facade arrangement

Section 5
Plastering works are performed
Installation of internal engineering networks
Facade arrangement
Work on the installation of lightning protection is performed
Installation of windows

Section 6
Plastering works are performed
Installation of internal engineering networks is completed
Facade arrangement
Installation of elevators
Installation of windows
Work on the installation of lightning protection is performed