Section 1
Completed concreting plate overlapping the level of commercial floor
The concreting of the parking walls is completed
Parking waterproofing
Section 2
Arrangement of monolithic frame 4 floors
Parking waterproofing is performed
Section 3
Waterproofing is completed
Start installation of window structures
Section 4
Installation of internal engineering networks
Plastering works are performed
Starts installation of elevators
Windows are installed
Facade arrangement
Section 5
Plaster works have been completed
Installation of internal engineering networks
Completed facade work on a living part
Starts installation of elevators
The window installation is completed
Section 6
Plaster works have been completed
The facade arrangement is completed
Installation of elevators is ongoing
Installation of windows is ongoing
Installation of balconies