January 2024

Intro Background Image

Sheet pile fencing – 100%;
Binding beam of the sheet pile fence – 100%;
Earthworks – 20% (soil development under Section 6 is completed, works under Section 5.1 are underway);
Water reduction – 50%;
Waterproofing – horizontal waterproofing of the foundation slab of Section 6 has been completed.
Foundation slab – 10% (completed crushed stone base, concrete preparation and over concrete according to Section 6);
Tower crane installation – 10%.

Sales department

Lviv, square Old Market, 8

Facebook Icon Instagram Icon