Section 1
Monolithic works on the underground part are underway. Waterproofing works are being carried out in parallel.
Section 2
Monolithic construction and waterproofing works continue.
Section 3
Wall masonry is in progress. Installation of ventilation shafts is ongoing.
Section 4
Installation of window structures has started.
Section 5
Wall plastering and installation of internal engineering networks are in progress.
Section 6
Internal engineering networks are being installed, wall plastering continues, and roofing works are underway.