April 2024

Intro Background Image

Works performed as of the beginning of April:

Dismantling works – completed;

Work on the pit of section 4 has been completed;

Horizontal waterproofing of the 1st p.c. – 45% (completed works on waterproofing section 5 of the residential and stylobate part);

Vertical waterproofing of the 1st p.c. – 10% (started works on waterproofing section 6);

Foundation slabs of the 1st p.k. – 45% (work has begun on the foundation slab of section 4);

Monolithic frame to department 0.000 of the 1st p.c. – 30% (works on section 6 are completed, work is being carried out on the floor slab on section 0.000 of the stylobate part of section 5 and on vertical structures on the -2nd floor of the parking lot of the residential part of section 5).

The monolithic frame is higher than 0.000 of the 1st p.c. – (work has begun on the arrangement of the vertical structures of the first floor of section 6).